Ficus Solar Energies Ficus Solar EnergiesKerala · Ernakulam & Thrissur

നെറ്റ് മീറ്ററിങ്

Net metering,and what KSEB actually does.

The paperwork half of a solar installation, and the half where Kerala is slower and stranger than the national guides suggest. Four steps, one of which turns sites down for reasons that have nothing to do with your roof — and one choice about the fixed charge that is routinely sold the wrong way round.

സോളാർ വെക്കുന്നതിന്റെ പേപ്പർ ജോലി. നാല് ഘട്ടം, 90–120 ദിവസം. ഇവിടെ എല്ലാം വിശദമായി.

From KSEB’s Tariff Revision Circular 2025–2027 and the regulator’s order of 22 September 2025 on the fixed charge for solar households, checked on 15 September 2026.

90–120

Days, application to net meter, in Kerala. Longer than most states and longer than most national guides admit.

₹47

Per kW a month — the flat fixed charge you are allowed to choose instead of the usual one. For a properly sized system it usually costs you money.

250

Units left on the bill after your panels. Above that, KSEB charges you by the time of day you use power.


മീറ്റർ എങ്ങനെ വായിക്കുന്നു

How the meter is read.

Almost everyone assumes export cancels import in the same instant. It does not, and the difference decides what you are billed.

KSEB bills you on what you took from the grid, less what you sent back, less anything left over from last month. Surplus is not paid for; it is banked and carried forward. So a bright February is not lost — it turns up on the next bill as a credit against what you use, rather than as money.

Which is why a system sized far past your own use earns less than it looks like it should: those extra units are never bought from you, and the subsidy stops at ₹78,000 whatever the size. Two separate reasons to size against your bill rather than against your roof.

And above 250 units, the clock starts to matter

If what is left on your bill is still above 250 units a month, KSEB charges you by the time of day you use power — 9 a.m. to 4 p.m. counts as solar hours, 4 p.m. to 9 a.m. does not. Worth knowing before you size anything, because the hours your panels work are not the hours most families use power. A house that cooks, washes and runs air conditioning after six is buying most of its electricity in the window its own roof cannot supply.

That does not make solar a bad idea. It makes when you use power part of the conversation, not just how much. The bill calculator shows which side of 250 you are on today →


ഫിക്സഡ് ചാർജ്

The fixed charge you still pay, and the choice about it.

The choice is real, the arithmetic behind it is not obvious, and most of the market has it backwards.

First, the part people are not told before they buy. Houses with solar pay the fixed charge like everyone else. It was challenged before the regulator in 2025 and the challenge failed. A customer who finds this out after the panels are up feels cheated, so it is said here plainly and before the sale rather than after it. (KSEB calls a household that generates its own power a prosumer; you will see the word on the forms.)

The same order created an option. Instead of the usual fixed charge, which rises and falls with your consumption, you may choose a flat ₹47 per kW a month on the size of your solar system — with at least one month’s written notice to KSEB.

It is usually the worse of the two, and it is routinely sold as the better. The tempting comparison is ₹141 a month for a 3 kW system against the ₹220 to ₹310 a big household pays today. That comparison is wrong: it sets the flat charge against your bill before solar. After solar your billed units collapse — and the usual fixed charge collapses with them, because it steps down through the same bands your units just fell through.

Which fixed charge wins, worked out against the bill you would have after solar
HouseholdSystemFlat ₹47/kWThe usual chargeWinner
300 units3 kW₹1,692/yr₹745/yrthe usual one, by ₹947
500 units5 kW₹2,820/yr₹925/yrthe usual one, by ₹1,895
400 units1 kW₹564/yr₹2,760/yrthe flat one, by ₹2,196
500 units2 kW₹1,128/yr₹2,760/yrthe flat one, by ₹1,632
The flat charge wins only where the system is deliberately small for the house — where the panels never cut the billed units enough to drop a band. For a properly sized system it costs you money. The estimator works out both for your own case and says which wins.

If you take one thing from this page: do not choose the flat charge because somebody called it the solar rate. Ask for both figures against the bill you would have after solar, in writing, and then choose. It is a month’s notice either way, not a life sentence.


നാല് ഘട്ടങ്ങൾ

The four steps, and how long they really take.

Written the way it actually runs in Kerala, including the gate that has nothing to do with your roof.

  1. Feasibility — including your transformer

    KSEB checks whether the distribution transformer feeding your street has the capacity to take what you would export. This is a real gate in Kerala and it rejects sites. It is not about your roof, it is not something a better quote fixes, and it is worth checking before you spend anything.

  2. Two applications, not one

    A set of annexures — 1, 2 and 3, filed at three different stages of the installation — goes to KSEB, and the subsidy application goes to the national portal. Both, not either. Filing one and assuming it covers the other is the most common way an application stalls quietly for a month.

  3. Installation and inspection

    The system goes up and KSEB inspects it before anything is energised against the grid. Commissioning ahead of approval is not a shortcut; it is how a subsidy claim fails.

  4. Net meter and agreement

    The net meter goes in and the net metering agreement is signed. The meter is rented, like the ordinary one: ₹30 a month single phase, ₹35 three phase.

Budget 90 to 120 days end to end. That is longer than most states and longer than most national guides admit. Anyone promising four weeks in Kerala has either not done it or is not telling you the truth.

It is also the reason the 31 March 2027 subsidy deadline is closer than it looks: four months of approval means an application started late in 2026 is not comfortable.

One more thing that can cap your system

Your roof is not the only limit. KSEB also looks at the load sanctioned on your connection — the figure on your bill — and the system you are allowed can be capped by it whatever your roof would hold. If you want something large, raise it at the feasibility stage, not after the panels are bought.


ചോദ്യങ്ങൾ

Questions about the approval.

The money questions are on the savings calculator and the subsidy ones are on the subsidy page.

If I export more than I import, does KSEB pay me?

Not in cash, month to month. What you send back is banked and carried into the next month’s bill as a credit against what you use. Which is why a system sized far past your own consumption earns less than it looks like it should — and why the ₹78,000 subsidy cap makes over-sizing poor value twice over.

What happens if the transformer on my street is full?

ട്രാൻസ്ഫോർമറിന് ശേഷിയില്ലെങ്കിൽ അപേക്ഷ നിരസിക്കപ്പെടാം.

The feasibility check can come back against you, and it is not a decision an installer can appeal on your behalf or design around. It is the single best reason to have the feasibility done before money changes hands rather than after — and it is why this page puts it first rather than fourth. If it does come back negative, that is a KSEB conversation about the transformer, on KSEB's timetable.

Can I switch the fixed charge later if I choose wrong?

Yes, with at least one month’s written notice to KSEB. So treat it as reversible rather than permanent — but get it right the first time by asking for both figures against the bill you would have after solar. The comparison that sells the flat rate uses your bill before solar, and that is the wrong one.

Why does Kerala take longer than other states?

Four gates, each with its own queue: feasibility including the transformer, the KSEB annexures, the inspection and the meter. The honest answer is that we can tell you the window — 90 to 120 days — without being able to tell you which desk your file is on today. What we can do is not promise four weeks, and tell you which gate you are at when you ask.

Do I need KSEB approval before I install?

Yes — feasibility comes first and the inspection comes before the system is energised against the grid. A system commissioned ahead of approval puts the subsidy claim at risk and leaves you arguing about something already screwed to your roof. Any installer suggesting the paperwork can follow the panels is arranging their schedule, not yours.

Does the net meter replace my existing meter?

A net meter is installed as part of the fourth step and it is rented separately — ₹30 a month single phase, ₹35 three phase. That rent, the fixed charge and the 10% electricity duty are the three things that survive on the bill whatever your panels do, which is why an honest post-solar estimate shows a small bill rather than none.

We supply the meter ourselves rather than wait for KSEB to issue one, which is usually a month or more on its own. That shortens the wait, not the bill: the ₹30 is KSEB’s standing rent for the meter and you pay it either way.


ബാക്കി കണക്കുകൾ

What it costs, and what the subsidy pays.

This page is the paperwork. The bill it changes, the system it approves and the subsidy it unlocks each have a page of their own.


ഇനി എന്ത്?

Ask about the transformer before you ask about panels.

It is the cheapest question on this page and the one that decides whether any of the rest applies to your address. Send us where you are and we will tell you what the feasibility is likely to say — and if it is bad news, you will have heard it before you spent anything. Ficus Solar Energies, across Kerala from Ernakulam and Thrissur, 4.9 ★ from 111 Google reviews.

കെഎസ്ഇബി അപ്രൂവലും പേപ്പർവർക്കും ഞങ്ങൾ ചെയ്തു തരും. വാട്ട്‌സാപ്പിൽ ബന്ധപ്പെടൂ.

No obligation, and no charge for the survey. See the work, the reviews and who we are →